Tower Crane & Heavy Lifting Permit Software: Governing Load Charts, Anti-Collision Zones, and Rigging Gear Inspections
Design the workflow
TL;DR — what you’ll learn
- Unverified radius-load combinations and underestimated rigging weight cause catastrophic crane overturns and jib collapses: When a site engineer plans a 6.8-tonne precast facade panel lift at a 42-meter radius by checking only the net panel weight—forgetting to add the 0.85-tonne spreader beam, 0.35-tonne hook block, and wire-rope fall weight—actual gross hook load exceeds the tower crane's Rated Capacity (SWL) at that radius by $15\%$, relying entirely on the Load Moment Indicator (LMI) not being bypassed in manual override mode.
- Statutory Form-II / Third-Party Competent Person load test certificates expire every 12 months (or after every mast jumping/climb): Under BOCW Central Rules, 1998 (Rules 56 & 62) and IS 13367, no tower crane, crawler crane, or passenger material hoist can operate without a valid Competent Person test certificate and verified Automatic Safe Load Indicator (ASLI / LMI) calibration—and every telescopic mast climb or tie-in collar addition requires a fresh structural and overload/limit-switch re-certification.
- Rigging gear sling-angle geometry multiplies leg tension exponentially: As the horizontal sling angle drops from $60^\circ$ to $30^\circ$, the tension in each sling leg doubles ($\text{Load Factor} = 1 / \sin 30^\circ = 2.000$), snapping wire-rope or webbing slings that appeared adequate on paper.
- Overlapping multi-crane slewing zones and high-gust wind speeds ($>36\text{ km/h}$ for large panels, $>72\text{ km/h}$ general shutdown) require hard digital permit locks: ERP lifting governance blocks electronic Permit-to-Lift (e-PTW) issuance whenever anemometer wind thresholds, expired third-party certificates, or uninspected quarterly colour-coded rigging gear are detected.

Illustrative EPC site office and plant readiness yard; not a client project site.
On major EPC and construction projects, tower crane & heavy lifting permit software: governing load charts, anti-collision zones, and rigging gear inspections breaks down when site execution logs, engineering revisions, and commercial ledgers update on different cut-offs. Without a shared verification gate, project controls teams discover quantity or specification mismatches only after billing or hand-over disputes surface.
Start by binding every field event to its approved baseline reference, physical inspection evidence, and named owner. A disciplined workflow separates provisional site observations from certified project records so exceptions are resolved before they distort cost or schedule reporting.
- Approved baseline scope
- 100 units
- Issued revision and WBS work package
- Field-logged progress
- 94 units
- Captured from site sheets and logs
- Certified & verified
- 88 units
- Passed inspection and tolerance check
- Quarantined variance
- 6 units
- Held pending engineering/commercial sign-off
Illustrative project control balance for EPC-117: baseline commitment, field observation, verified quantity, and quarantined exception.
Read the visual as text
Approved baseline scope: 100 units. Issued revision and WBS work package. Field-logged progress: 94 units. Captured from site sheets and logs. Certified & verified: 88 units. Passed inspection and tolerance check. Quarantined variance: 6 units. Held pending engineering/commercial sign-off.
Original explanatory visual: NextEdge Labs. Illustrative records, not client results.
- STEP 01Freeze baseline & package rules
Owner: Planning / controls lead
Lock revision, WBS code, and measurement basis.
- STEP 02Capture site event & evidence
Owner: Site engineer
Record physical progress, test logs, and lot references.
- STEP 03Verify tolerance & completeness
Owner: QA / QS verifier
Check captured evidence against contract and design gates.
- STEP 04Certify ledger posting
Owner: Project manager
Approve reconciled quantities and release downstream billing.
Certify the record and update the WBS progress and cost ledger.
Route the disputed delta to the exception register without overwriting baseline history.
Return path: Attach the signed engineering disposition or joint re-measurement sheet, then re-run verification step 03.
Read the workflow as text
1. Freeze baseline & package rules (Planning / controls lead) → 2. Capture site event & evidence (Site engineer) → 3. Verify tolerance & completeness (QA / QS verifier) → 4. Certify ledger posting (Project manager). After step 3, ask: Do site measurements, revisions, and quality records reconcile within tolerance? Yes: Certify the record and update the WBS progress and cost ledger. No: Route the disputed delta to the exception register without overwriting baseline history. Return: Attach the signed engineering disposition or joint re-measurement sheet, then re-run verification step 03.
Workflow: NextEdge Labs. Apply the project’s actual authority and procedures.
The Reader Decision: Why Paper Lifting Permits Fail to Prevent Overturning Moments and Jib Collisions
For an EPC Director of EHS (Environment, Health & Safety), Head of Plant & Machinery (P&M), or High-Rise Project Director managing a congested construction site with 4 to 12 overlapping luffing/hammerhead tower cranes, dual-cage passenger hoists, and 250-tonne crawler cranes, Heavy Lifting Operations represent the single highest catastrophic-risk exposure on site. A single tower crane jib failure, dropped precast segment, or passenger hoist free-fall results in fatal injuries, immediate statutory Stop-Work Orders under the BOCW Act, 1996, criminal liability for the Project Manager, and months of schedule paralysis.
Yet on most construction sites, lifting governance relies on clipboards of paper Permit-to-Lift (PTW) forms filled out hurriedly by a site supervisor each morning. This paper workflow fails in four critical ways:
- Ignoring Gross Hook Load and Radius-Load Chart Derating: Paper lift permits ask the supervisor to write down "Load Weight (MT)" and "Crane Capacity (MT)." Frequently, the supervisor writes the crane's *maximum capacity near the mast* (e.g., "12 MT Tower Crane") rather than the Rated Capacity at the exact pick-and-place operating radius ($R_{\max}$) (which may be only $2.9\text{ MT}$ at the $60\text{ m}$ jib tip!), and forgets to add the weight of the hook block, hoist wire rope, spreader beam, shackles, and slings.
- Sling Angle Tension Multiplication and Uninspected Rigging Gear: Under BOCW Rule 70 and ASME B30.9, chains, wire-rope slings, D-shackles, and synthetic webbing slings must undergo statutory examination by a Competent Person every 12 months and quarterly site colour-coded visual inspection (e.g., Q1 Green, Q2 Yellow, Q3 Blue, Q4 Red). On paper-managed sites, damaged slings with broken wires or low-headroom rigging setups with $30^\circ$ horizontal sling angles are used without computing the Sling Angle Tension Factor, overloading individual legs by $100\%$.
- Unchecked Mast-Climb Re-Certification and LMI Override Keys: When a high-rise tower crane undergoes telescopic climbing (jacking) and adds a new mast tie-in collar at Floor 24, its structural anchor bolts, torque values, and Load Moment Indicator (LMI / ASLI) cut-out switches must be re-tested before returning to service. Additionally, if the physical LMI bypass key is left in the operator cabin to push through a heavy lift, a paper permit never detects that the crane is operating with its overload cut-out defeated.
- Overlapping Slewing Zones and Wind-Gust Blindness: On sites with multiple tower cranes whose jibs overlap in plan view (but step down at different hook heights), disabling or failing to verify the Electronic Anti-Collision & Zoning System before shift handover risks a load hoist wire from the upper crane snagging the counter-jib or slewing jib of the lower crane—especially when wind speeds exceed 20 knots ($36\text{ km/h}$) during large-surface-area formwork or precast panel lifts.
The operational decision for EPC safety and P&M leaders is to replace paper lift checklists with an ERP Digital Lifting Permit, Load-Chart Verification, and Asset Interlock System governed by BS 7121 and BOCW Central Rules.
Regulatory & Engineering Standards: BOCW Rules 55–73, BS 7121, and Rigging Physics
1. Gross Hook Load and Crane Load-Chart Utilization Ratio ($\eta_{\text{crane}}$)
Under BS 7121-1 and IS 13367, a crane's load chart specifies the Rated Capacity ($RC(R)$) at each operating radius $R$ (measured horizontally from the centre of rotation of the slewing ring to the vertical centreline of the hook). The Total Gross Hook Load ($W_{\text{gross}}$) is the sum of all components suspended from the jib point:
$$W_{\text{gross}} = W_{\text{net}} \times \gamma_{\text{dyn}} + W_{\text{rigging}} + W_{\text{spreader}} + W_{\text{hook}} + W_{\text{rope}}$$
Where: - $W_{\text{net}}$ is the verified dry/wet weight of the payload (from GFC drawing or manufacturer shipping manifest, plus any entrained concrete/water/mud allowance). - $\gamma_{\text{dyn}}$ is the dynamic / tandem amplification factor ($\gamma_{\text{dyn}} = 1.00$ for standard single-crane static pick; $\gamma_{\text{dyn}} = 1.25$ to $1.33$ per crane during Tandem Lifts under BS 7121 to account for unequal load sharing and out-of-plumb hoist lines). - $W_{\text{rigging}}$ is the combined weight of shackles, wire-rope slings, chains, and turnbuckles. - $W_{\text{spreader}}$ is the tare weight of any lifting beam or spreader frame. - $W_{\text{hook}}$ and $W_{\text{rope}}$ are the weights of the main hook block and the suspended multi-fall hoist wire rope (when not already net-deducted in the OEM load chart).
The Crane Capacity Utilization Percentage ($\eta_{\text{crane}}$) at the maximum radius $R_{\max} = \max(R_{\text{pick}}, R_{\text{place}})$ is:
$$\eta_{\text{crane}} = \left(\frac{W_{\text{gross}}}{RC(R_{\max})}\right) \times 100\%$$
2. Multi-Leg Sling Angle Tension Physics
When a load of total suspended weight $W_{\text{suspended}} = W_{\text{net}} + W_{\text{spreader}}$ is lifted using an $N$-leg sling bridal at an angle $\theta$ measured from the horizontal (or $\alpha = 90^\circ - \theta$ measured from the vertical), the tension $T_{\text{leg}}$ in each active load-bearing leg is:
$$T_{\text{leg}} = \frac{W_{\text{suspended}}}{N_{\text{eff}} \times \sin\theta} = \frac{W_{\text{suspended}}}{N_{\text{eff}} \times \cos\alpha}$$
Crucially, under BS 7121 and EN 13414-1 for rigid payloads lifted with a 4-leg sling, because minor dimensional tolerances prevent all four legs from sharing the load equally across two diagonals without an equalizing beam, only $N_{\text{eff}} = 2$ or $N_{\text{eff}} = 3$ legs (depending on rigidity and centre-of-gravity symmetry; standard conservative engineering practice uses $N_{\text{eff}} = 2$ for rigid 4-point picks without a spreader) may be assumed to carry the entire load! Additionally, horizontal sling angles $\theta < 45^\circ$ (or vertical angles $\alpha > 45^\circ$) are heavily restricted, and $\theta < 30^\circ$ is strictly prohibited across EPC safety codes.
Recomputed Illustrative Math: Precast Facade Spandrel Lift & Tandem Gantry Girder Lift
Let us trace two real-world high-rise and industrial lifting scenarios processed by the ERP Lifting Permit Engine to see how automated physics checks prevent crane overloading and sling failure.
Scenario A: Single Tower Crane Lift of a Precast Architectural Spandrel Panel
A high-rise commercial tower uses a 12-Tonne Hammerhead Tower Crane (`TC-02`, Jib Length $60\text{ m}$) to lift a precast concrete spandrel beam from the trailer bay (Pick Radius $R_{\text{pick}} = 28\text{ m}$) and place it on the building perimeter (Place Radius $R_{\text{place}} = 44\text{ m}$): - Net Precast Panel Weight ($W_{\text{net}}$): $4.80\text{ MT}$ ($4,800\text{ kg}$) per GFC shop drawing. - Modular Steel Spreader Beam ($W_{\text{spreader}}$): $0.65\text{ MT}$ ($650\text{ kg}$). - 4-Leg Wire-Rope Sling Assembly + 4 Bow Shackles ($W_{\text{rigging}}$): $0.18\text{ MT}$ ($180\text{ kg}$). - 4-Fall Hook Block + Suspended Hoist Rope ($W_{\text{hook+rope}}$): $0.42\text{ MT}$ ($420\text{ kg}$). - Tower Crane `TC-02` OEM Load Chart Rated Capacity: - At $R_{\text{pick}} = 28\text{ m}$: $RC(28\text{ m}) = 9.40\text{ MT}$ - At $R_{\text{place}} = 44\text{ m}$: $RC(44\text{ m}) = \mathbf{6.50\text{ MT}}$ (governing radius $R_{\max} = 44\text{ m}$).
Step 1: Gross Hook Load & Crane Capacity Utilization Check
$$W_{\text{gross}} = 4.80 + 0.65 + 0.18 + 0.42 = \mathbf{6.05\text{ MT}}$$ $$\eta_{\text{crane}} = \left(\frac{6.05\text{ MT}}{6.50\text{ MT}}\right) \times 100\% = \mathbf{93.08\%}$$
Notice the trap: - If a site supervisor looked only at the net panel weight ($4.80\text{ MT} / 6.50\text{ MT} = 73.85\%$), they would mistakenly classify this as a Routine Lift ($<75\%$ SWL) requiring no Appointed Person engineering review! - Because the ERP includes spreader, rigging, and hook block weights, $\eta_{\text{crane}} = 93.08\% > 85\%$, automatically reclassifying the operation as a Critical Lift ($>85\%$ Rated Capacity) requiring Appointed Person (AP) signoff, wind-speed lock at $\le 28\text{ km/h}$ ($7.8\text{ m/s}$ for large wind-sail precast panels), and dedicated rigger exclusion-zone barricading.
Step 2: Sling Leg Tension Verification Above the Spreader Beam
A 2-leg wire-rope top bridal ($N_{\text{eff}} = 2$) connects the crane hook to the two pad-eyes of the spreader beam. Each sling leg has a length $L_{\text{sling}} = 4.00\text{ m}$, and the pad-eyes on the spreader beam are spaced $5.656\text{ m}$ apart ($2.828\text{ m}$ from centreline), creating a horizontal sling angle $\theta = 45^\circ$ ($\sin 45^\circ = 0.7071$): - Total Load Suspended Below Top Bridal ($W_{\text{susp}}$): $$W_{\text{susp}} = W_{\text{net}} + W_{\text{spreader}} + W_{\text{lower\_rigging}} = 4.80 + 0.65 + 0.08 = 5.53\text{ MT}$$ - Actual Tension per Top Bridal Leg ($T_{\text{leg}}$ at $\theta = 45^\circ$): $$T_{\text{leg}} = \frac{5.53\text{ MT}}{2 \times \sin 45^\circ} = \frac{5.53\text{ MT}}{2 \times 0.7071} = \frac{5.53\text{ MT}}{1.4142} = \mathbf{3.91\text{ MT per leg}}$$
If the rigger selected a pair of $3.2\text{ MT}$ SWL single-leg wire-rope slings assuming "$2 \times 3.2\text{ MT} = 6.4\text{ MT} > 5.53\text{ MT}$," each sling leg would be overloaded by $22.2\%$ ($3.91\text{ MT vs } 3.20\text{ MT}$)! The ERP Rigging Engine rejects the $3.2\text{ MT}$ sling barcode and mandates a minimum $4.5\text{ MT}$ SWL per leg (22 mm diameter Grade 1960 steel-core wire-rope sling) + $4.75\text{ MT}$ Alloy Bow Shackles.
Scroll horizontally to see all columns.
| Parameter | Naive Manual Estimate | Audited ERP Engineering Calculation | Safety Governance Outcome |
|---|---|---|---|
| Governing Radius ($R_{\max}$) | $28\text{ m}$ Pick ($RC = 9.40\text{ MT}$) | $44\text{ m}$ Place ($RC = 6.50\text{ MT}$) | Prevents jib-tip overload during luffing/trolley out |
| Evaluated Hook Load | $4.80\text{ MT}$ (Net Panel Only) | $6.05\text{ MT}$ (Gross Hook Load) | Adds $1.25\text{ MT}$ of tare rigging/spreader/hook weight |
| Capacity Utilization ($\eta_{\text{crane}}$) | $73.85\%$ ("Routine Lift") | $93.08\%$ ("Critical Lift $>85\%$") | Escalates permit to Appointed Person (BS 7121) |
| Top Bridal Sling Tension ($T_{\text{leg}}$) | $2.77\text{ MT}$ (Ignores $45^\circ$ angle) | $3.91\text{ MT}$ ($\div \sin 45^\circ$) | Blocks $3.2\text{ MT}$ sling; enforces $\ge 4.5\text{ MT}$ SWL leg |
End-to-End ERP Workflow, Role Owners, Exceptions, and Recovery
1. Crane, Hoist & Rigging Gear Statutory Asset Registry
- Owner: Project P&M Head & Site EHS Manager.
- Workflow: Every tower crane, mobile/crawler crane, passenger/material hoist, spreader beam, wire-rope sling, and shackle is registered in the ERP with a unique QR/RFID tag before entering the site gate:
- Lifting Appliances (Cranes & Hoists): Stores OEM digital load charts ($RC$ vs Radius $R$ for each jib configuration and reeving fall count, i.e., 2-fall vs 4-fall), BOCW Form-II Competent Person Load Test Certificate (12-month expiry + mandatory reset flag upon mast climb/jumping), LMI calibration seal number, and anti-collision zoning matrix.
- Rigging Gear & Lifting Tackles: Stores SWL, leg count, length, annual Form-II test expiry, and Quarterly Colour-Code Inspection Status (
GREEN,YELLOW,BLUE,RED). Any sling not inspected in the current quarter is automatically flaggedQUARANTINED_EXPIRED_COLOUR_CODE.
2. Daily Pre-Shift Operator & Anemometer Telemetry Gate
- Owner: Crane Operator & Lifting Supervisor.
- Workflow: Before energizing the crane slewing/hoisting contactors each morning, the operator completes the mobile Pre-Use Functional Checklist verifying hoist/trolley/slew limit switches, brake holding test, wire-rope drum spooling, Passenger Hoist Drop-Test / Overspeed Governor Validity (verified every 90 days), and Anti-Collision System Active Status. Mast-head anemometer wind-speed readings stream into the ERP dashboard:
- $< 28\text{ km/h}$ ($< 15\text{ knots}$): All approved lifts permitted.
- $28\text{ to } 36\text{ km/h}$ ($15\text{ to } 20\text{ knots}$): High-wind-area lifts (formwork shutters, precast facade panels, rebar cages) automatically suspended.
- $> 50\text{ to } 72\text{ km/h}$ (per OEM manual): Full crane shutdown; jib placed in free-slew weathervane mode clear of obstacles.
3. Digital Permit-to-Lift (e-PTW) & Appointed Person Signoff
- Owner: Lifting Supervisor & Appointed Person (BS 7121 Certified).
- Workflow: To request a lift permit, the engineer selects the Crane ID, enters Pick/Place coordinates (or selects them on the site BIM plan so the ERP computes $R_{\text{pick}}$ and $R_{\text{place}}$ automatically), inputs payload weight and dimensions, and scans the QR codes of the shackles and slings. The ERP computes $W_{\text{gross}}$, $\eta_{\text{crane}}$, and $T_{\text{leg}}$, and enforces tiered signoff:
- Tier 1 — Routine Lift ($\eta_{\text{crane}} \le 75\%$, standard geometry): Approved by Lifting Supervisor + Crane Operator.
- Tier 2 — Non-Routine Lift ($75\% < \eta_{\text{crane}} \le 85\%$, or near live utilities): Requires P&M Engineer + EHS Officer co-signoff.
- Tier 3 — Critical / Tandem / Man-Basket Lift ($\eta_{\text{crane}} > 85\%$, Tandem Lift, Blind Lift, or Night Critical Pick): Requires a dedicated CAD Rigging Study, Tandem 25%–33% Derating Calculation (ensuring neither crane exceeds $75\%$ of its individual rated capacity), and digital approval by the certified Appointed Person (AP) and Project Director.
4. Exceptions & Recovery Playbook
- Exception A: Tower Crane Telescopic Mast Climb (Jumping) Triggers Immediate Permit Lock
- *Scenario:* Over the weekend, the rigging crew jacks up Tower Crane
TC-02by adding 3 mast sections ($9\text{ m}$ height increase) and installs a new structural building tie-in frame at Floor 18. On Monday morning at 08:00, the civil supervisor tries to issue a routine rebar lift permit onTC-02. - *Recovery:* Logging a Mast Climbing / Configuration Change Permit automatically flips
TC-02asset status toLOCKED_PENDING_POST_CLIMB_CERTIFICATION. The ERP blocks all lifting permits until the P&M Engineer uploads: (1) Structural Engineer's Tie-In Bracket Concrete Cube Strength ($\ge 25\text{ MPa}$) & Bolt Torque Certificate, (2) Mast Verticality Survey ($\le 1:1000$ plumb tolerance), and (3) Competent Person Post-Climb Form-II & LMI Re-Calibration Signoff. - Exception B: Anti-Collision Transponder Fault Between Two Overlapping Tower Cranes
- *Scenario:* The electronic zoning sensor on Tower Crane
TC-01(lower crane) loses radio communication withTC-02(upper crane whose jib sweeps acrossTC-01's counter-jib zone). - *Recovery:* The operator reports the fault on the morning checklist. The ERP immediately locks independent overlapping operation and issues a Controlled Single-Slewing / Dedicated Banksman Protocol: either one crane is parked outside the interference sector with its slew brake locked, or the ERP mandates a dedicated radio-linked Slew-Zone Signalman (Banksman) assigned exclusively to the overlap boundary until the OEM technician replaces the transponder module.
Implementation Action Plan: 4 Steps to Eliminate Crane Overloads and Rigging Failures
- Digitize OEM Load Charts by Jib Length and Reeving Configuration (2-Fall vs 4-Fall): Do not store a tower crane in your ERP simply as a "10-Tonne Crane." Load its complete radius-vs-capacity curve so the permit system automatically evaluates capacity at $\max(R_{\text{pick}}, R_{\text{place}})$.
- Mandate Automated Tare-Weight Addition and Sling-Angle Math ($\div \sin\theta$) on Every e-PTW: Force the permit calculator to add hook block, hoist wire, spreader beam, and rigging weights to the net payload, and block any rigging configuration where horizontal sling angle $\theta < 45^\circ$ without Appointed Person override (and hard-block $\theta < 30^\circ$).
- Interlock BOCW Form-II Validity, Mast-Climb Status, and Quarterly Rigging Colour Codes: Configure the e-PTW engine so that scanning an expired sling QR code or selecting a crane past its 12-month Competent Person test date (or uncertified after a mast jump) makes permit generation impossible.
- Enforce a 75% Individual Capacity Cap on All Tandem Lifts: Whenever two cranes lift a single load together, require the ERP to apply a minimum $\gamma_{\text{dyn}} = 1.25\text{ to } 1.33$ amplification factor (capping each crane at $\le 75\%$ of its rated capacity at the governing radius) to guard against centre-of-gravity shifts and out-of-plumb side loading.
Frequently Asked Questions
How do high-rise and industrial sites govern tower-crane third-party load test validity, wind-speed anemometer shutdown logs, overlapping-jib anti-collision zones, and critical tandem-lift permits?
Teams should govern crane management software by linking every transaction to its source evidence, timestamp, and assigned owner before permitting downstream posting. Distinct from EPC-031 (equipment utilization/fuel); EPC-117 covers rigging gear (shackles, slings, spreader beams) colour-code quarterly inspections, load-moment-indicator (LMI) calibration records, and Appointed Person lift-plan signoffs. Rather than relying on informal spreadsheet overrides, the workflow enforces a documented verification gate and preserves the original observation whenever a correction is recorded.
How does construction safety software handle exceptions and mismatches?
When a discrepancy occurs during construction safety software, the system routes the blocked record into an owned exception queue rather than silently dropping or auto-adjusting the balance. Assigned operational, quality, and finance owners must review and approve exceptions before posting. Each exception retains the original quantity, date, and counterparty reference until the designated reviewer resolves the variance with supporting evidence.
What should teams test before automating lifting plan software?
Before scaling lifting plan software, run a bounded pilot using historical records that include partial receipts, late updates, duplicate messages, and rejected lines. Verify that the integration preserves idempotency, maintains a clear segregation of duties between operational entry and financial approval, and produces an auditable trail for every state transition.
How do project teams close the loop with an auditable action plan?
A reliable control loop lets project managers, site engineers, and commercial reviewers trace every transaction back to its approved drawing, inspection lot, and measurement sheet.
- Freeze the baseline scope, revision code, and unit-of-measure rules for one work package before capturing site events.
- Verify physical measurements, test certificates, and counterparty sign-offs at the designated hold point.
- Route any out-of-tolerance variance into an explicit exception queue with a named owner and target resolution date.
- Post only certified quantities and reconciled costs into the project ERP and WBS progress ledger.
Compare this workflow with your current setup
Share the step that takes the most manual work, the systems involved and the exceptions your team handles. That gives us a concrete starting point for comparing approaches.
References and further reading
Sources checked 20 October 2026. The worked examples and diagrams are original editorial explanations, not client results.
- ERPNext documentation — Stock EntryStock Entry purposes and Add to Transit subsection