Facade & Unitized Curtain Wall Software: Governing Cast-In Bracket Surveys, PMU Testing, and Field Hose-Test Signoffs
Design the workflow
TL;DR — what you’ll learn
- Structural concrete slab-edge tolerances ($\pm 25\text{ mm}$) clash directly with unitized curtain-wall bracket adjustment limits ($\pm 15\text{ mm}$): When high-rise RCC floor slabs are poured without verifying 3D Total Station coordinates of Cast-In Anchor Channels (Halfen/Jordahl) and slab-edge lines prior to panel dispatch, factory-glazed unitized curtain-wall panels arrive at the floor edge and cannot be plumbed—forcing dangerous field-slotting of aluminium brackets or costly customized hook-on adapters.
- Serial-level factory silicon structural glazing (SSG) cure logs and Performance Mock-Up (PMU) signoffs must gate facade shipping: Under CWCT Standards and ASTM E283/E331, no serialized unitized panel (UCP-FL18-N042) should leave the assembly plant until its 2-part structural silicone snap-time, butterfly mix test, and Shore-A hardness / peel adhesion test are linked to its batch barcode.
- Field water-penetration testing (AAMA 501.2 nozzle hose test & ASTM E1105 chamber test) must be executed every 3 to 5 floors before interior drywall conceals the perimeter: Waiting until building completion to test curtain-wall stack joints and cruciform gaskets means any monsoon leak requires ripping out finished tenant gypsum walls and ceilings across multiple floors.
- Perimeter slab-edge fire-stop safing (NBC 2016 Part 4) requires 100% photo-verified closure before floor handover: The gap ($100\text{ mm}$ to $180\text{ mm}$) between the RCC slab edge and the back of the curtain-wall spandrel panel acts as a vertical chimney unless high-density mineral wool safing and elastomeric smoke sealant are inspected and signed off bay-by-bay.

Illustrative EPC site office and plant readiness yard; not a client project site.
On major EPC and construction projects, facade & unitized curtain wall software: governing cast-in bracket surveys, pmu testing, and field hose-test signoffs breaks down when site execution logs, engineering revisions, and commercial ledgers update on different cut-offs. Without a shared verification gate, project controls teams discover quantity or specification mismatches only after billing or hand-over disputes surface.
Start by binding every field event to its approved baseline reference, physical inspection evidence, and named owner. A disciplined workflow separates provisional site observations from certified project records so exceptions are resolved before they distort cost or schedule reporting.
- Approved baseline scope
- 100 units
- Issued revision and WBS work package
- Field-logged progress
- 94 units
- Captured from site sheets and logs
- Certified & verified
- 88 units
- Passed inspection and tolerance check
- Quarantined variance
- 6 units
- Held pending engineering/commercial sign-off
Illustrative project control balance for EPC-124: baseline commitment, field observation, verified quantity, and quarantined exception.
Read the visual as text
Approved baseline scope: 100 units. Issued revision and WBS work package. Field-logged progress: 94 units. Captured from site sheets and logs. Certified & verified: 88 units. Passed inspection and tolerance check. Quarantined variance: 6 units. Held pending engineering/commercial sign-off.
Original explanatory visual: NextEdge Labs. Illustrative records, not client results.
- STEP 01Freeze baseline & package rules
Owner: Planning / controls lead
Lock revision, WBS code, and measurement basis.
- STEP 02Capture site event & evidence
Owner: Site engineer
Record physical progress, test logs, and lot references.
- STEP 03Verify tolerance & completeness
Owner: QA / QS verifier
Check captured evidence against contract and design gates.
- STEP 04Certify ledger posting
Owner: Project manager
Approve reconciled quantities and release downstream billing.
Certify the record and update the WBS progress and cost ledger.
Route the disputed delta to the exception register without overwriting baseline history.
Return path: Attach the signed engineering disposition or joint re-measurement sheet, then re-run verification step 03.
Read the workflow as text
1. Freeze baseline & package rules (Planning / controls lead) → 2. Capture site event & evidence (Site engineer) → 3. Verify tolerance & completeness (QA / QS verifier) → 4. Certify ledger posting (Project manager). After step 3, ask: Do site measurements, revisions, and quality records reconcile within tolerance? Yes: Certify the record and update the WBS progress and cost ledger. No: Route the disputed delta to the exception register without overwriting baseline history. Return: Attach the signed engineering disposition or joint re-measurement sheet, then re-run verification step 03.
Workflow: NextEdge Labs. Apply the project’s actual authority and procedures.
The Reader Decision: Why Disconnected Factory Glazing Logs and Site Survey Sheets Cause Multi-Crore Facade Delays
For a High-Rise Project Director, Facade Package Manager, or Building Envelope Consultant delivering a 40-to-80-storey commercial tower, luxury residential skyscraper, or airport terminal, the Unitized Curtain Wall (UCW) Envelope is both the architectural face of the project and the critical-path gate for Building Weather-Tightness ("Dry-In")—the milestone that allows interior MEP, drywall, flooring, and joinery trades to commence without rain or wind damage.
Yet on most high-rise construction projects, the Civil RCC Frame Contractor, the Off-Site Facade Fabrication Factory, and the Site Facade Installation Crew operate on disconnected spreadsheets and CAD files. This disconnect creates four severe technical and commercial failures:
- The Civil Tolerance vs Facade Bracket Collision ($\pm 25\text{ mm}$ vs $\pm 15\text{ mm}$): Standard structural concrete codes (IS 456 / ACI 117 / BS 5606) allow RCC slab-edge plan position and cast-in channel placement tolerances of $\pm 20\text{ mm}$ to $\pm 25\text{ mm}$, whereas standard extruded aluminium unitized curtain-wall starter/mulion brackets are engineered with serrated T-bolt slots and horseshoe shims accommodating only $\pm 12\text{ mm}$ to $\pm 15\text{ mm}$ in-out ($Y$), $\pm 15\text{ mm}$ left-right ($X$), and $\pm 10\text{ mm}$ up-down ($Z$) adjustment. When the site survey team does not feed 3D Total Station coordinates of the cast-in channels back to the ERP *immediately after slab de-shuttering*, the installation crew discovers 8 floors later while hanging a $350\text{ kg}$ glass panel from a monorail hoist that the slab edge protrudes by $+28\text{ mm}$—halting the entire floor's facade erection!
- Unlinked Factory Structural Silicone (SSG) Batch & Cure Quality: In a 4-sided Structural Silicone Glazing (SSG) unitized system, the double-glazed insulated glass unit (IGU) is held onto the aluminium frame against positive/negative wind loads ($2.5\text{ kPa}$ to $4.5\text{ kPa}$) solely by two-part structural silicone sealant. If a factory mixing pump suffers an off-ratio catalyst drift and the ERP does not link every panel serial barcode to its Daily Butterfly Test (void-free mix), Snap-Time Test, and H-Piece / Peel Adhesion Test before releasing the panel from the curing rack to the transport stillage, panels with un-crosslinked silicone get hung on the 45th floor.
- Skipped Progressive AAMA 501.2 Field Hose Tests Before Interior Fit-Out: Under CWCT Section 12 and AAMA 501.2, installed curtain-wall joints (especially the 4-way cruciform intersection where horizontal stack joints meet vertical split mullions) must undergo calibrated nozzle water testing ($205\text{ to } 240\text{ kPa}$ ($30\text{–}35\text{ psi}$) water pressure from $305\text{ mm}$ distance at $5\text{ mins per } 1.5\text{ m}$ joint) at early floors (e.g., Floor 3–4, Floor 12, Floor 25). When contractors skip progressive hose tests and close interior drywall mullions, a single displaced EPDM cruciform plug or pinched wiper gasket leaks across 6 floors during the first cyclone.
- Payment Disputes Over "Supply at Site" vs "Installed, Torqued, Fire-Stopped & Weather-Sealed": Facade subcontracts typically split payment across Extrusion/Glass Procurement ($30\%$), Factory Unitization ($25\%$), Site Delivery ($15\%$), Panel Hanging & Alignment ($15\%$), Perimeter Fire-Stop & Sealant ($10\%$), and Water Test/Handover ($5\%$). Without a visual ERP Elevation Matrix (Floor $\times$ Grid Bay) tracking the exact lifecycle state of all 6,500 serialized panels, quantity surveyors overpay for panels stacked in stillages or hung without torque/fire-stop signoff.
The architectural decision for high-rise EPC leaders is to deploy an ERP Serialized Facade Digital Twin, Bracket Tolerance & Envelope QA Engine that links every floor-bay coordinate (Floor 22, Bay N-14) from cast-in channel survey through factory silicone curing, monorail installation, torque verification, AAMA 501.2 water testing, and NBC Part 4 fire-stopping.
Engineering & Regulatory Standards: CWCT, AAMA 501.2, ASTM E1105, and Structural Silicone Bite Math
1. Structural Silicone Glazing (SSG) Bite Width & Deadload Support Math (ASTM C1401)
In a unitized curtain-wall panel subjected to design wind load $W_{\text{wind}}\text{ (kPa)}$ over glass short-span dimension $B_{\text{short}}\text{ (m)}$, the required minimum Structural Silicone Bite Width ($b_{\text{bite}}$, in mm) using a structural silicone with allowable design tensile stress $\sigma_{\text{allow}} = 138\text{ kPa}$ ($20\text{ psi}$) is governed by the trapezoidal wind-load formula:
$$b_{\text{bite}} = \frac{0.5 \times W_{\text{wind}} \times B_{\text{short}}}{\sigma_{\text{allow}}} \times 1,000\quad \left(\text{Minimum } b_{\text{bite}} \ge 6.0\text{ mm}; \text{ glue thickness } e_{\text{glue}} \ge 6.0\text{ mm}\right)$$
2. 3D Bracket Tolerance Envelope & Stack-Joint Differential Movement
At each floor slab edge, every unitized mullion is hung on an extruded aluminium/steel bracket anchored to a cast-in channel (Halfen HTA-CE). The ERP evaluates three orthogonal survey offsets $(\Delta X, \Delta Y, \Delta Z)$ at every grid node $(i,j)$ against the Theoretical Building Facade Line (BFL): - In-Out Offset ($\Delta Y = Y_{\text{survey}} - Y_{\text{BFL}}$): Standard bracket serrated slot range $= \mathbf{\pm 15.0\text{ mm}}$. - Left-Right Offset ($\Delta X = X_{\text{survey}} - X_{\text{BFL}}$): Standard T-bolt channel sliding range $= \mathbf{\pm 20.0\text{ mm}}$ (provided T-bolt stays $\ge 50\text{ mm}$ clear of channel end-anchor). - Vertical Elevation Offset ($\Delta Z = Z_{\text{survey}} - Z_{\text{BFL}}$): Standard levelling jack-bolt / horseshoe shim range $= \mathbf{\pm 12.0\text{ mm}}$. - Horizontal Stack-Joint Engagement ($H_{\text{stack}}$): The male/female transom stack joint between Floor $n$ and Floor $n+1$ is designed with a nominal $20.0\text{ mm}$ to $25.0\text{ mm}$ movement joint to absorb live-load slab deflection ($\Delta_{\text{LL}} \approx L/360 \text{ to } L/500$), long-term concrete column creep/shrinkage, and thermal expansion of the $4.0\text{ m}$ tall aluminium mullion ($\Delta L_T = \alpha_{\text{Al}} \cdot L \cdot \Delta T \approx 23 \times 10^{-6} \times 4,000\text{ mm} \times 45^\circ\text{C} = \mathbf{4.14\text{ mm}}$). If cumulative vertical installation error reduces the stack joint at assembly below $16.0\text{ mm}$, live-load slab deflection will cause glass-to-metal contact and spontaneous glass breakage!
Recomputed Illustrative Math: Floor-24 Bracket Tolerance Clash Resolution & SSG Bite Audit
Consider a 52-Storey Commercial High-Rise Tower installing a Unitized Curtain Wall (`4,200 Panels`, nominal panel size $1,500\text{ mm wide} \times 4,000\text{ mm floor-to-floor height}$) designed for a Peak Corner Zone Wind Load $W_{\text{wind}} = 3.60\text{ kPa}$.
Step 1: Verifying Factory SSG Bite Width & Glue Joint Geometry (Corner Panel UCP-FL24-W02)
For Corner Panel UCP-FL24-W02 ($B_{\text{short}} = 1.500\text{ m}$, $L_{\text{long}} = 4.000\text{ m}$, IGU glass weight $= 258\text{ kg}$ supported on 2 EPDM-padded aluminium setting blocks at quarter points): - Required Minimum Structural Silicone Bite ($b_{\text{bite}}$) at $W_{\text{wind}} = 3.60\text{ kPa}$ and $\sigma_{\text{allow}} = 138\text{ kPa}$: $$b_{\text{bite,req}} = \frac{0.5 \times 3.60\text{ kPa} \times 1.500\text{ m}}{138\text{ kPa}} \times 1,000 = \frac{2.700}{138} \times 1,000 = \mathbf{19.57\text{ mm}}\implies \text{Design Specified Bite} = \mathbf{21.0\text{ mm}}$$ - Factory Quality Control Scan before Stillage Dispatch: - Actual measured SSG bite width across all 4 perimeter sides: $21.4\text{ mm}$ (Glue thickness $= 8.0\text{ mm}$, Aspect Ratio $21.4 / 8.0 = 2.68 \le 3.0$, PASS). - Two-part silicone mix ratio ($10:1$ by weight): $10.1 : 1.0$; Snap-time $= 34\text{ mins}$; 7-day Shore-A Hardness $= \mathbf{42\text{ Shore A}}$ ($\ge 35\text{ Shore A}$ minimum for transport release); Peel adhesion $= 100\%$ cohesive failure (PASS).
Step 2: Total Station Slab-Edge & Cast-In Channel Survey Audit on Floor 24 (West Elevation, 20 Bays)
Immediately after Floor 24 slab stripping (6 weeks before Floor 24 panels are scheduled to be hung), the survey team uploads Total Station coordinates for the 21 Bracket Positions (`BRK-W01` to `BRK-W21`) into the ERP Tolerance Engine:
Scroll horizontally to see all columns.
| Bracket Node ID | Slab Edge Offset ($\Delta Y_{\text{slab}}$, mm) | Cast-In Channel Offset ($\Delta Y_{\text{chan}}$, mm) | Lateral Offset ($\Delta X$, mm) | Level Offset ($\Delta Z$, mm) | Standard Bracket Capacity ($\Delta Y: \pm 15\text{ mm}$) | ERP Automated Engineering Action |
|---|---|---|---|---|---|---|
| `BRK-W01` to `W15` | $-6\text{ to } +9\text{ mm}$ | $-5\text{ to } +8\text{ mm}$ | $-8\text{ to } +11\text{ mm}$ | $-4\text{ to } +5\text{ mm}$ | Within $\pm 15\text{ mm}$ | GREEN: Issue Standard Bracket TYPE-A + Standard Shim Pack |
| `BRK-W16` & `W17` | $+24.0\text{ mm}$ (Bulge) | $+22.0\text{ mm}$ (Outward) | $+6.0\text{ mm}$ | $+3.0\text{ mm}$ | FAIL ($> +15\text{ mm}$) | RED (Protruding Slab): Auto-raise Civil NCR for $12\text{ mm}$ concrete edge grinding + issue Short-Reach Bracket TYPE-S |
| `BRK-W18` & `W19` | $-26.0\text{ mm}$ (Recessed) | $-25.0\text{ mm}$ (Inward) | $-12.0\text{ mm}$ | $-6.0\text{ mm}$ | FAIL ($< -15\text{ mm}$) | AMBER (Recessed Slab): Issue Pre-Engineered Extended Cantilever Bracket TYPE-XL ($+35\text{ mm}$ reach) + Post-Installed Hilti Anchor |
| `BRK-W20` & `W21` | $+4.0\text{ mm}$ | $+5.0\text{ mm}$ | Channel Missing / Buried | $+2.0\text{ mm}$ | FAIL (No Channel) | RED: Authorize Ferro-Scan rebar mapping + Post-Installed Undercut Expansion Anchors (Hilti HDA-T) + Proof Pull-Out Test ($1.5\times$ load) |
Quantifying the Financial & Schedule Savings of the 6-Week Early Survey Gate
- Without the ERP 3D Survey Gate: Stillage
STIL-FL24-Warrives on Floor 24; the installation crew hangsW01throughW15and then hits the $+24\text{ mm}$ concrete bulge atW16and the $-26\text{ mm}$ recess atW18. Six panels (W16toW21) remain un-hung in a gaping hole on Floor 24 for 21 days while custom extended brackets are structurally designed, extruded/fabricated, and tested—blocking Floor 24 Dry-In and delaying interior MEP and drywall handover by 3 weeks (Standby Hoist + Interior Delay Cost = ₹34.50 Lakhs). - With the ERP 6-Week Early Survey Gate: The $+24\text{ mm}$ concrete grinding NCR and the 2
TYPE-XLextended brackets are resolved 5 weeks before the panels arrive on site. All 20 panels on Floor 24 West are hung, plumbed, and torqued in a single continuous 2-day shift (Zero Standby Delay).
End-to-End ERP Workflow, Role Owners, Exceptions, and Recovery
1. Performance Mock-Up (PMU) Approval Gate Before Mass Extrusion & Glazing
- Owner: Facade Package Manager & Envelope Specialist Consultant.
- Workflow: Before releasing mass production of unitized panels in the factory, the ERP requires uploading the signed accredited Laboratory Performance Mock-Up (PMU) Test Certificate covering: Air Infiltration (ASTM E283), Static & Dynamic/Aero-Engine Water Penetration (ASTM E331 / AAMA 501.1), Design Wind Load Structural Deflection ($\le L/175$ per ASTM E330), Inter-Storey Seismic Drift (AAMA 501.4), and Proof Load ($1.5\times$ design wind load).
2. Serialized Factory Assembly, SSG Curing & Stillage Dispatch Tracking
- Owner: Factory QA Manager & Site Logistics Coordinator.
- Workflow: Every unitized panel receives a permanent weather-resistant QR / RFID Serial Tag (`UCP-FLxx-Byy`) bonded inside the mullion glazing pocket. The ERP tracks 4 factory gates: (1) Frame Crimping/Assembly, (2) IGU Glazing & Two-Part SSG Pumping (linked to pump butterfly/snap-time batch ID), (3) Curing Rack Residency ($\ge 7\text{ to } 14\text{ days}$ + Shore-A & Peel Adhesion signoff), and (4) Floor-Matched Stillage Loading (ensuring Stillage
STIL-FL24-W1contains panels loaded in exact reverse-hanging sequence so the floor crew never double-handles glass on the slab).
3. Site Bracket Survey, Panel Hanging, AAMA 501.2 Water Test & Fire-Stop Closure
- Owner: Site Facade Engineer, QA Inspector & Civil Interface Engineer.
- Workflow: On the visual ERP Building Elevation Grid (`52 Floors` $\times$ `80 Bays`), each cell advances through colour-coded states:
SURVEYED_BRACKET_APPROVED(3D Total Station offset verified within $\pm 15\text{ mm}$ or customTYPE-XLbracket fitted).PANEL_HUNG_AND_PLUMBED(Deadload jack-bolt levelled; stack joint verified at $20\text{ mm} \pm 2\text{ mm}$; EPDM cruciform splice plug wet-sealed with silicone).FINAL_TORQUED( Bracket anchor bolts and wind-restraint shear pins torqued with calibrated wrench; horseshoe shims tack-welded/locked).WATER_TEST_PASSED(Progressive AAMA 501.2 Field Hose Test and ASTM E1105 Chamber Test signed off with zero internal water droplets over 15 minutes).PERIMETER_FIRESTOP_CLOSED(Mineral-wool safing compressed $\ge 25\%$ in slab-edge gap + $3\text{ mm}$ dry-film elastomeric fire/smoke spray verified per NBC 2016 Part 4). Hard Gate: Interior drywall framing and raised-floor closure on that floor are enabled only when $100\%$ of bays reach State 5!
4. Exceptions & Recovery Playbook
- Exception A: Field Hose Test (AAMA 501.2) Detects Water Ingress at a 4-Way Cruciform Stack Joint
- *Scenario:* During the Floor 12 AAMA 501.2 nozzle test ($220\text{ kPa}$ water spray for 5 minutes at the cruciform joint between
UCP-FL12-N08andN09), water droplets appear at the internal transom drainage weep zone inside the room. - *Recovery:* Under AAMA 501.2 Diagnostic Protocol, the ERP logs a Water Penetration NCR and places an immediate Hold on Interior Drywall Closure for Floors 10–14 North. The QA team performs sequential bottom-up masked hose testing to isolate the entry point (identifying an un-primed EPDM cruciform overlapping flap), injects neutral-cure weather silicone into the cruciform splice marriage joint across the affected batch of panels, waits 72 hours for cure, and conducts a Mandatory Re-Test on the Repaired Bay plus Two Adjacent Control Bays before lifting the hold.
- Exception B: Nickel Sulfide ($\text{NiS}$) Spontaneous Toughened Glass Breakage or Tower Crane Load Strike
- *Scenario:* After hanging Panel
UCP-FL31-E12, the outer pane of its heat-soaked double-glazed unit shatters due to a falling scaffold clamp from Floor 40. - *Recovery:* The ERP scans
UCP-FL31-E12's QR code to retrieve the exact Factory IGU Glass Makeup Code (e.g., $8\text{ mm}$ Low-E Solar Control Toughened Heat-Soaked Outer $+ 16\text{ mm}$ Argon Spacer $+ 13.52\text{ mm}$ Laminated Inner, exact mm dimensions and coating batch), auto-orders a replacement IGU from the glass processor, and tracks the High-Altitude Rope-Access / BMU De-Glazing & Re-Glazing Method Statement and structural silicone cure clock.
Implementation Action Plan: 4 Steps to Deliver Leak-Free High-Rise Facades on Schedule
- Mandate a 3D Total Station Slab-Edge & Cast-In Channel Survey Within 7 Days of Slab Stripping: Import survey coordinates into the ERP 6 weeks ahead of facade hanging so concrete bulges ($>+15\text{ mm}$) and recessed slabs ($<-15\text{ mm}$) are resolved with grinding or pre-engineered
TYPE-XLbrackets long before stillages arrive. - Block Factory Stillage Dispatch Without Serial-Linked SSG Butterfly and Peel-Adhesion Logs: Require every unitized panel barcode to carry its two-part silicone mix ratio, Shore-A hardness ($\ge 35$), and cohesive peel test signoff before leaving the factory curing rack.
- Execute Progressive AAMA 501.2 Field Hose Tests Every 4 to 5 Floors Before Interior Fit-Out: Never allow interior gypsum drywall or false ceilings to cover perimeter curtain-wall mullions until that floor zone's field water test and cruciform joint audit are signed off.
- Enforce a 100% Photo-Verified Perimeter Fire-Stop Gate (NBC Part 4) Per Bay: Require a geo-tagged photo of the compressed mineral-wool safing and smoke-sealant DFT at every single slab-edge bay before releasing the facade subcontractor's installation milestone payment.
Frequently Asked Questions
How should facade contractors track total-station cast-in-channel bracket surveys, PMU performance mock-up chamber approvals, serialized unitized-panel installation, and field hose-test signoffs?
Teams should govern facade engineering software by linking every transaction to its source evidence, timestamp, and assigned owner before permitting downstream posting. Distinct from general glazing; EPC-124 reconciles structural slab edge tolerances (+/- 25mm) against bracket shimming limits before hanging serialized unitized curtain-wall panels. Rather than relying on informal spreadsheet overrides, the workflow enforces a documented verification gate and preserves the original observation whenever a correction is recorded.
How does curtain wall tracking handle exceptions and mismatches?
When a discrepancy occurs during curtain wall tracking, the system routes the blocked record into an owned exception queue rather than silently dropping or auto-adjusting the balance. Assigned operational, quality, and finance owners must review and approve exceptions before posting. Each exception retains the original quantity, date, and counterparty reference until the designated reviewer resolves the variance with supporting evidence.
What should teams test before automating high rise construction software?
Before scaling high rise construction software, run a bounded pilot using historical records that include partial receipts, late updates, duplicate messages, and rejected lines. Verify that the integration preserves idempotency, maintains a clear segregation of duties between operational entry and financial approval, and produces an auditable trail for every state transition.
How do project teams close the loop with an auditable action plan?
A reliable control loop lets project managers, site engineers, and commercial reviewers trace every transaction back to its approved drawing, inspection lot, and measurement sheet.
- Freeze the baseline scope, revision code, and unit-of-measure rules for one work package before capturing site events.
- Verify physical measurements, test certificates, and counterparty sign-offs at the designated hold point.
- Route any out-of-tolerance variance into an explicit exception queue with a named owner and target resolution date.
- Post only certified quantities and reconciled costs into the project ERP and WBS progress ledger.
Compare this workflow with your current setup
Share the step that takes the most manual work, the systems involved and the exceptions your team handles. That gives us a concrete starting point for comparing approaches.
References and further reading
Sources checked 20 October 2026. The worked examples and diagrams are original editorial explanations, not client results.
- ERPNext documentation — Stock EntryStock Entry purposes and Add to Transit subsection